---On
Nov. 25, 2004, Yatai Engineering Supervision & Consultation
Co Ltd. of HRC took part in the bidding for the supervision
on the Diaoliang Reclamation Project in Zhoushan, and successfully
won the bidding.
The project is located in Lianghengshan,
Zhanmo Town, Putuo District, Zhoushan City. The construction
includes the shoal reclamation of 2205 mu (1 mu = 0.0677
hectare); the permanent standard sea dike of 5557 m for
against 50-year flood; the separated bank of 2346 m; and
two gates as well. The accumulative filling volume of earth
and rock is estimated to be 4.157 million m3. The total
investment of the project amounts to RMB 290,000,000Yuan.
As planned, the project will be
started in December 2004, and completed in December 2007,
with the total construction duration of 36 months. (2004-12-13)